Major milestone reached at Forbach modernisation project - International Water Power

Major Milestone Reached at Forbach Modernisation Project

Excavation of the new machine cavern at the Forbach hydropower complex in Germany's Black Forest has been completed, according to Tractebel.

Crews removed 48,000 m³ of rock to create a cavern measuring 125m in length, 19m in width, and up to 42m in height.

All equipment will be located within the new underground hall along with associated auxiliary systems.

Tractebel is leading the planning consortium on behalf of EnBW Energie Baden-Württemberg AG, working with GEOCONSULT and Lahmeyer International.

No direct quote available in the text.

Author's summary: Forbach hydropower complex excavation completed.